What is the typical range of factor of safety for landslide remediations?
1.15 to 1.50
What is an example of a condition that is not reasonably foreseeable in landslide remediation?
Developments that introduce new sources of water
How many variables are listed in Table 13.1 as affecting the factor of safety for remediation?
5
What is considered a reasonable "worst condition" for groundwater levels in remedial calculations?
Groundwater reaching the surface when it is normally very close to the surface.
When might a geotechnical practitioner and owner agree to a marginal stabilization of a landslide?
When any improvement in stability is preferable to the status quo.
What does the term "permanent stability" refer to in the context of landslide remediation?
The cessation of movement or reduction to a low rate of creep after remediation has been applied.
Why is it important to warn property owners about potential movements after remediation?
To prevent rumors that the landslide is still unstable when it has been stabilized.
Based on the author's experience, what is the approximate maximum rise of groundwater above normal high winter levels in clay soils of moderate slopes?
6 feet
How many passes of a heavy bulldozer (Caterpillar D-8 or larger) are required to compact each lift of rockfill?
At least four passes
What is the recommended lift thickness for spreading rockfill in most landslide work?
12 to 24 inches
How does a rockfill stockpile with 30% by weight of gravel-size or larger pieces appear visually?
The sand fraction appears to cover about one-half of the surface of the stockpile
What potential legal issue is associated with rockfill slopes?
Lawsuits from rocks falling or bouncing down slopes, damaging property or injuring people
Why is it important to limit the percentage of material passing the No. 4 sieve in rockfill?
To ensure point-to-point contact between coarser rock fragments
What is the recommended maximum percentage of fines (passing No. 200 sieve) for rockfill in critical applications?
3 percent by weight
What is the recommended outer slope design for rockfill when space is limited or maximum overburden stress is needed?
1V:1H
What shape requirement is specified for rockfill material?
The long dimension should not be more than three times the shortest dimension
What is the primary goal of groundwater lowering in landslide remediation?
Increasing slope stability
Why are theoretical solutions to drainage options often challenging to apply in practice for landslides?
Landslides often have heterogeneous and anisotropic soil properties
What are two examples of conditions that are not reasonably foreseeable in landslide areas?
New sources of water and changes in land use
Why is long-term monitoring of groundwater levels important after implementing drainage measures?
To track the progress of groundwater lowering and measure its ability to permanently lower the water table and suppress seasonal fluctuations
How does surficial creep affect structures built on clay slopes?
It can cause separation between concrete slabs and soil, and minor distortion of wood structures and walls
What potential issue should be considered immediately after drainage measures have been installed?
Groundwater lowering may not immediately stabilize a landslide
How can engineering geologists predict the duration of the transition period for groundwater lowering?
By using experience or conducting trials such as pump tests
What is a key consideration when estimating the effectiveness of groundwater lowering measures?
The time required to reach steady-state long-term conditions
What is the recommended outer slope design for rockfill in landslide applications?
1½:1 (horizontal:vertical)
What is the minimum soil cover required over geotextile before equipment is allowed to pass over it?
1 foot
What is the typical fully saturated density range for high-quality rockfill used in landslide applications?
126-131 lb./cu. ft.
How should geotextile be placed on slopes in relation to the line of maximum slope?
With overlaps along the line of maximum slope
What is the minimum overlap required when placing geotextile in landslide applications?
12 inches
Why is pea gravel considered an ideal drainage material?
It has a uniform particle size with no fine sand, silt, or clays present
How does the strength of rockfill change with increasing effective overburden stress?
It decreases slightly
How does crushed hard quarry rock compare to pea gravel as a drainage material?
Crushed rock has higher strength but is more compressible
Why is a gap-graded gravel unsuitable for drainage purposes?
It is likely to segregate during handling, causing local pockets of sand or open-graded gravel
How are filter materials often placed when used as a separator between cut slopes in native soils and rockfill?
In small heaps or windrows, pushed up the slope just ahead of the rockfill placement
What advantage does a soil filter layer have over a geotextile fabric?
It provides better shear strength, especially for steep slopes
How thick should a soil filter layer, such as clean sandy gravel, typically be?
At least 12 to 15 inches thick measured normal to the slope
Why do many geotechnical practitioners prefer to specify filter fabric rather than graded filter soils when placing rockfill against native soils?
It avoids the need to specify and import a material that may be difficult to manufacture or be available only from a remote source
What is the recommended maximum percentage of fines passing the No. 200 sieve for a free-draining filter material?
3 to 5% by weight, based on wet sieving
What is a potential drawback of using geotextiles instead of soil filter layers?
Geotextiles generally have a lower shear resistance and could provide a surface of weakness
What is the primary purpose of filter layers in soil engineering?
To prevent migration of fines from one soil to another
Who is typically considered to have the most knowledge of preexisting ground conditions in a dewatering controversy?
The geotechnical consultant
How does the traditional practice in construction work approach the specification of dewatering methods?
It defers the methods of construction to the contractor
What should be included in the plans and specifications for a project requiring temporary dewatering?
Dewatering requirements and a separate item in the bill of quantities
What are two applications of filter materials in landslide remediation work?
Separation layer between headscarp and rockfill, and covering active springs or seepage areas
What is an alternative approach to specifying dewatering methods in the project specifications?
Requiring the contractor to employ an experienced groundwater specialist
What is a potential consequence of not specifying appropriate dewatering methods in the original contract?
Increased construction costs due to claims and litigation
Why do contractors often opt for the least expensive dewatering technique when preparing bids?
To keep their bid price competitive relative to other bidders
What is the primary purpose of dewatering during construction of remedial measures for landslides?
To prevent loss of ground, protect safety, and preserve ground integrity
How does the size of a landslide affect the difficulty of modeling and the required factor of safety?
Small landslides are more difficult to model accurately and require a higher factor of safety.
What are the key variables to consider when setting the factor of safety for landslide remediation?
The type of landslide movement, amount of study performed, size of the landslide, potential consequences, and experience of the geotechnical engineer.
Why does the author generally oppose setting a minimum value for the factor of safety in landslide remediation?
It ignores the effect of different variables on the reliability of stability analyses.
Who should determine the factor of safety needed for permanent stability in landslide remediation?
The geotechnical engineer using professional judgment.
How does the factor of safety in an actual landslide event differ from a potential landslide scenario?
In an actual landslide event, the factor of safety has a known value of 1.00.
What are the main uncertainties in stability analyses of an actual landslide event?
The shear strengths and piezometric levels on the slip surfaces at the time of failure.
What is the primary goal of landslide remediation?
To restore permanent stability to a landslide against existing and reasonably foreseeable future conditions.
How can the variables for setting the factor of safety be organized to help determine an appropriate value?
They can be put into a matrix.
How can internal erosion be prevented when using rockfill in landslide remediation?
By placing a separation layer, such as filter fabric or filter layer, between the fine-grained soils and the rockfill.
What factors should be considered when evaluating the suitability of a proposed landslide remedial technique involving temporary excavations?
The engineer should assess the landslide slope, proximity of roads, buildings, buried utilities, and the risk of damage from potential movements.
What potential risk is associated with temporary excavations during landslide remediation?
Temporary excavations may reactivate movements upslope of the excavation.
What is the recommended shape for rock pieces used in landslide remediation projects?
Rock pieces should not be platelike, with the long dimension no more than three times the shortest dimension.
When is the optimal time to schedule landslide remediation work in the Pacific Northwest?
Late August to early October, when groundwater levels are seasonally near their lowest levels.
What are the two main disadvantages of using rockfill for landslide remediation projects?
The two main disadvantages are cost and the need for a filter fabric or filter layer.
Why is crushed rounded river gravel not an acceptable substitute for shot rock in landslide remediation?
The strength of crushed river gravel is substantially lower than shot hard rock from a quarry.
How can the risk of damage from temporary excavations be mitigated in landslide remediation projects?
By carefully assessing the landslide slope, proximity of structures, and scheduling work during low groundwater periods.