Questions in this set (20)
How can project managers use the information from critical path analysis?
To identify activities that directly impact the project completion date and manage them closely
What are the three main factors that determine dependencies between activities?
Mandatory dependencies, discretionary dependencies, and external dependencies
Why should project managers avoid fitting the schedule to meet desired project end dates?
To ensure a realistic and achievable project timeline
What is the first step in developing an initial project schedule?
Identify immediate predecessors for all activities
How many days would it take to complete 40 activities in sequence if each takes 2.5 days?
100 days
What is the purpose of drawing a network diagram in project scheduling?
To visually represent the sequence and relationships between project activities
What does a finish-to-start (FS) dependency relationship indicate?
The predecessor must finish before the successor can start
What additional information is needed to create a detailed project schedule?
Length of each activity and the order of performing activities
How does a start-to-start (SS) dependency differ from a finish-to-finish (FF) dependency?
SS requires the predecessor to start before the successor can start, while FF requires the predecessor to finish before the successor can finish
How does analyzing a project's network diagram help in schedule development?
It identifies critical paths, their lengths, and slack times of non-critical paths
How does the 'Reporting Rule' impact task duration in project scheduling?
No task should be longer than the time between two status points
Why is it important to consider the time between status points when determining task duration?
It ensures regular progress updates and allows for timely identification of issues
What is the recommended duration for work packages according to the 'Easier-To Rule'?
Work packages should be 1 to 10 days long
How does the 8/80 rule guide work package size in project management?
No task should be less than 8 labor hours or greater than 80 labor hours
What is the purpose of a Combined Activity/Milestone and Gantt Chart in project management?
To provide a comprehensive view of activities, milestones, and their timelines in one visual format
How does knowing the duration of 40 activities, each taking 2.5 days, contribute to determining the overall project duration?
It provides partial information, but the activity sequence is also needed to calculate the total duration
What additional information is needed to create a project schedule after having the project objectives, scope, deliverables, WBS, and list of activities?
Duration of each activity and the sequence of activities
What is the primary benefit of using a Work Breakdown Structure in graphical format?
It provides a visual hierarchy of project components, making relationships easier to understand
What is the primary purpose of a Work Breakdown Structure (WBS) in project management?
To break down the project into smaller, manageable work packages
How does a Gantt Chart differ from a Milestone List in project scheduling?
A Gantt Chart visually represents activities over time, while a Milestone List is a simple text-based list of key events