What is the primary purpose of grading in landslide mitigation?
To flatten the surface slope angle to a stable angle
What is the recommended minimum compaction for fill in buttress construction?
90 percent of the maximum density as per ASTM D1557
How do cut-and-fill transitions relate to differential settlement?
They are a special case of differential settlement
What factors are most important for stability on difficult lots?
Material strength, compaction, and aspect of bedding and other discontinuities
Why are bedrock and fill material impacted differently during ground shaking?
Because of their dissimilar material properties
How does the use of lightweight fill materials contribute to landslide prevention?
It lightens the weight at the head of the slide
What is the primary cause of fill displacement failures?
Static gravity force
What is the most common fill displacement hazard?
Differential settlement
Who wrote the book on grading practices in southern California mentioned in the text?
Michael Scullin
What is the primary focus of Chapter 7 in mitigating seismic hazards?
The use of grading techniques, surface and ground water control, and geotechnical ground improvement methods
What are the two main objectives of the chapter as stated in the text?
Describe and recommend geotechnical techniques that lessen earthquake-induced hazards, and promote these techniques
How much surface settlement is generally accepted for liquefaction hazards?
1"/30'
What is the commonly accepted factor of safety for slopes under static loads?
> 1.5
What are the three general ways to treat earthquake-induced hazards according to the text?
Avoid the hazard, reduce the hazard to an acceptable level, and accommodate the hazard
When did local implementation of the Seismic Hazards Mapping Act (SHMA) begin?
1990
What does the text suggest about the long-term success of hazard mitigation?
It often depends on timely inspection, maintenance and ongoing repair
What is the primary goal of the Seismic Hazards Mapping Act regarding development and safety?
To balance development costs and safety by requiring adequate site analysis and promoting appropriate mitigation techniques
How is the factor of safety defined in slope stability analysis?
The ratio of resisting forces to driving forces
Why might multiple mitigation methods be used at a single construction site?
To address different geotechnical hazards present and accommodate various types of structures proposed
What are the primary geotechnical hazards addressed by the mitigation techniques discussed in the text?
Earthquake-induced landslide and liquefaction hazards
What are the two types of grading commonly used to mitigate landslide hazards in California?
"Hillside" construction of building pads and "flat land" construction of engineered mats
What foundation system is recommended for typical single-family residential houses to accommodate differential settlements up to one inch?
A post-tensioned slab foundation system
When is a slope considered to be at the point of failure?
When the factor of safety equals one
How can landslide and liquefaction hazards be fully eliminated according to the text?
By removal or densification of all potentially unstable soils, or permanently lowering the groundwater
How do earth flows differ from debris flows in terms of movement speed?
Earth flows are characteristically slow moving
What is the primary trigger for debris flows according to the text?
Prolonged rainfall following a period of less intense precipitation
How does the geomorphic character of a soil flow depend on the properties of the slide mass?
It depends on the particle size, slope, and water content
How does increased pore water pressure affect the shear strength of soil in shallow disrupted slides?
It reduces the shear strength
What are the two main types of soil flows categorized by grain size?
Debris flows and earth flows
How can offsite flows be mitigated according to the text?
Using catchment basins, protective structures, and requiring setback distances
What percentage of slope gradient is most commonly associated with debris flows?
Greater than 65 percent
What is the most common mitigation solution for soil flow hazards?
Providing an adequate setback from the runout zone
What role do earthquakes play in triggering shallow disrupted slides?
They induce dynamic compaction and increase pore water pressure
Why are debris flows considered a significant threat to life and property?
They can move very rapidly and travel relatively long distances
How does the density of fill material typically compare to underlying materials?
Fill is typically less dense than underlying materials
What term describes shallow disrupted slides composed of loose combinations of soil, surficial deposits, rock fragments, weathered rock, and vegetation?
Soil flows
What is the primary goal of grading in cut-fill transitions?
To minimize the difference in bearing capacity across the cut-fill boundary
What is the primary issue associated with Cut-and-Fill transitions in construction?
Differential settlement
What is a common grading solution for excess settlement in deep canyon fill failures?
Flatten the canyon walls and compact the fill in "zones"
How does scarification contribute to the stability of cut-fill transitions?
It provides a bond between the fill material and the underlying native rock
What factor often leads to a gradual reduction in soil strength in deep fills?
Increased pore pressure
Why is ongoing maintenance crucial for the long-term stability of cut and fill slopes?
To ensure drainage and erosion control measures remain effective
What is the minimum compaction requirement for fill material according to the text?
90 percent of the maximum density as per ASTM D 1557
What is a recommended mitigation practice for stabilizing settlement failures at cut-fill transitions?
Over-excavate and grade the bedrock surface in multiple steps
What is the overall grading goal for mitigating rotational slides?
To reduce driving forces in upper parts and increase resisting forces in the toe area of the slope
How are rotational slides characterized?
By a somewhat cohesive slide mass that rotates along a relatively deep failure plane
What can happen if naturally occurring landslides are not sufficiently removed before engineered fill is placed?
Movement can be reactivated along the pre-existing failure plane and transmitted to the surface
What is a commonly used method to prevent pore water pressure build-up in constructed engineered fill?
Installation of sub-drain galleries
What are the four general categories of earthquake-induced slope failures mentioned in the text?
Rotational landslides, fill displacements, soil flows, and rock falls
What are the key steps involved in stabilizing a landslide mass during re-construction?
Remove unstable soil and rock, regrade to a stable configuration, scarify the failure plane, and install sub-drains
What is the principal failure mechanism in rotational landslides?
The loss of shear strength at depth along a rupture surface
Why have grading practices for hillside projects been better developed than those for flatland projects?
Rainfall-induced slope failures occur more often and are more widespread than earthquake-induced liquefaction failures